Reported from CSPPLAZA: At 0:51 on June 17th, the Shouhang Dunhuang 100MW towe CSP plant which was independently designed and invested by Beijing Shouhang IHW Resources Saving Technology Company Co., Ltd., achieved full-load power generation. At the same time, day-and-night power generation of the plant under summer conditions exceeded 1800MWh, and all indicators met or exceeded the design value.
On June 16, under the excellent weather, the plant performed full load operation verification . During the continuous verification process of nearly 20 hours, the best operation record shows that the molten salt temperature at the outlet of the receiver reached 565℃; the main steam temperature and pressure were respectively 539.59℃&13.2 MPa; the maximum output power of the steam turbine generator is 100.8 MW.
All the main indicators are better than the design value, and the subsystems such as concentrating, heat absorbing, heat storage, heat exchange and power generation are running normally and stably.
This is another important milestone in the operation of the plant after the first 34 hours of continuous power generation under spring conditions from April 15th to 17th reaching nearly 1670MWh.
Please click to know more details about the project: Overview of Shouhang Dunhuang 100MW Molten Salt Tower CSP Project
Beijing Shouhang IHW Resources Saving Technology Company Co., Ltd. is sure to attend the China International CSP Conference(CPC2019)to be held on 10-12,July, in Suzhou, China. During the conference, Shouhang will share in-depth the construction and operation experience of the project.
To know more details about the project, please join in the CPC2019. For more information about the conference, please contact: Catherine@cspplaza.com