The Installation of Solar Field for Gonghe 50MW Tower CSP Project Basically Completed
2019-01-16 19:30:00    

Reported from CSPPLAZA: On January 14th, 2019, one of China’s first batch of CSP demonstration projects – the Power Construction Corporation of ChinaQinghai Gonghe 50MW Tower Project successfully completed the installation of the 29,788 heliostats, which marked the installation work of solar field has been basically completed.

Zhejiang SUPCON Solar Technology Co., Ltd. provides the project with equipment supply, installation and technical services of the concentrating collector system. A total of 30,016 heliostats are configured. All the heliostats were assembled and installed within 7 months.

The project is located in an ecological solar power park about 12 kilometers southwest of Gonghe County, Hainan Prefecture, Qinghai Province, which is equipped with a 6-hour molten salt heat storage system.

Judging from the current progress,the project is expected to be connected to the grid by June,2019.which will be the forth CSP projects in China to be put into operation.